The most important solar PV decision on a UK new build is when to install — during construction or as a post-completion retrofit. The financial gap between the two is material (about 21% per kW on DESNZ's 2025/26 means), but the more interesting differences are in integration, warranty and aesthetic outcomes. This article is one part of our wider guide to solar panels for new builds, which covers the Future Homes Standard rule, sizing and costs.
Cost difference: new build wins by about a fifth
A 4.40 kWp array (the Part L 2026 reference for a 50 m² ground floor) installed in-roof during construction runs at about £1,200/kWp, roughly £5,280 (Spirit Energy publishes ~£1,200/kWp ex VAT and scaffolding for roof-integrated solar). The same capacity retrofitted to the completed dwelling would be about £8,900 at £2,022 per kW, the 2025/26 mean for domestic retrofits in DESNZ's solar PV cost data; in the same data, domestic new-build installs averaged £1,599 per kW, about 21% less. The cost gap reflects: (1) labour — retrofit requires a separate scaffold mobilisation and additional plot access vs new-build factory pre-fit; (2) on-roof vs in-roof — retrofit invariably uses on-roof systems (in-roof retrofit requires stripping the existing roof, uneconomic); (3) design stage — in-roof panels displace tile cost when specced before the roof package is ordered.
Integration with ASHP, battery and MVHR
New-build installation lets the solar PV system integrate cleanly with the rest of the building services. Inverter and battery locations are planned into the M&E layout at RIBA Stage 3, with adequate clearance, ventilation and serviceability. ASHP and PV controls share a common BEMS where appropriate. MVHR ducting routes around inverter heat dissipation. Retrofit installations work around the existing layout — inverters end up in suboptimal locations (under stairs, behind boiler cupboards), service routing improvised, and post-install commissioning of the integrated control system can take days that would have been hours on a planned new build.
FHS compliance only works at new-build phase
The Future Homes Standard 40% PV requirement applies to new dwellings — there is no equivalent retrofit requirement. Building a new dwelling without FHS-spec PV is not legally compliant from 24 March 2027. Retrofitting to an FHS-non-compliant dwelling is voluntary. This is the underlying reason new-build installation is universal across volume housebuilder programmes from 2027.
Warranty and EPC outcomes differ
New-build installations are typically commissioned with an EPC band A or upper B rating because all building services are FHS-compliant. Retrofit PV onto a 2021-spec dwelling typically lifts EPC from band C/D to band B at best — the fabric and heating system limit the upside. On a new build, ask the structural warranty provider (for example NHBC, LABC Warranty or Premier Guarantee) what it requires for the PV system before the roof is built. Retrofit PV on an existing home is covered by the installer workmanship warranty and the component warranties instead.
Aesthetic and sales-value outcomes
New-build installations almost always specify in-roof PV — flush with the roof tile or slate line. Retrofit installations almost always specify on-roof — visibly mounted above the tile line on rails. Estate agent feedback from 2025 buyer panels: in-roof installations contribute meaningfully to sale price (4-6% premium on EPC A vs B); on-roof retrofit shows less impact (1-3% premium) because the visible panel array is perceived as added equipment rather than integrated design.
When retrofit is the right choice
Three scenarios where retrofit makes sense despite the cost premium: (1) homeowner buying an existing 2024-vintage non-PV dwelling and seeking to upgrade — retrofit is the only option; (2) developer with existing land bank of pre-FHS plots in build-out — completing to 2021 spec under the transitional period and retrofitting if and when buyer demand justifies; (3) housing association with stock acquired pre-FHS that needs energy upgrades for tenant fuel-poverty intervention — retrofit accelerates outcomes. Outside these cases, new-build phase installation is the clear preference.
The strategic lesson
For any UK new-build project commencing planning from 2026 forward, treat solar PV as an integral building service rather than an optional bolt-on. Engage the PV designer at RIBA Stage 2, lock per-plot pricing at land bid, specify in-roof systems with factory pre-fit on panelised roof cassettes where applicable. The cost saving versus retrofit is meaningful, but the integration and warranty advantages are what make the choice obvious.